Client Background & Challenge

Hewlett Packard (HP) needed a full, ground-up racking system for its 125,000 sq. ft. manufacturing warehouse in Chippewa Falls, WI. The space was a blank slate: a completely empty building with no existing rack to remove and no live operations to protect. This gave our installation team plenty of room to receive, unload, stage, and install the heavy-duty racking for this facility. AK’s design team custom-designed a heavy-duty, high-bay Ridg-U-Rak selective rack system around HP’s current sit-down forklifts.

The scale of the order comprised the real challenge. Hundreds of frames, thousands of beams and wire decks, and a full protection package had our project management team working hard to get the right materials to the site at the right time. The project depended heavily on clear coordination and an installation crew that could keep pace.

System Specifications

Comprehensive Rack Protection Package

Site Conditions & Constraints

The warehouse was empty throughout the project, so the installation team had unrestricted access to the full floor with no staff, product, or active operations to work around. The main constraint was logistics, not space: materials for this project shipped from multiple trucking companies, and every delivery had to align with the installation schedule to keep the crew moving.

Solution & Design Approach

AK designed the system around HP’s standard sit-down forklifts, using 24′ teardrop frames paired with 8′ and 10′ beams and galvanized waterfall wire decking. The teardrop-style rack keeps future reconfiguration simple, and pairing the frame, beam, and deck capacities gives HP a robust, well-matched system. Because the project required no seismic calculations or special engineering, the design process stayed straightforward and the team could focus on material coordination and a fast install.

Installation Highlights

While the installation was originally scheduled for four weeks, the AK crew finished in one. Using scissor lifts and forklifts, the team moved quickly through the open floor, and the empty building allowed work to run without pauses or sequencing around other operations.

Coordinating deliveries from several different trucking companies was the biggest logistical hurdle. Careful tracking and communication kept every shipment arriving when needed, and the logistics were managed without stalling the timeline.

Outcomes & Results

Know What You Need?

Shop In Stock and Quick Ship Systems

Want to View Our Catalog?

Shop Our Material Handling & Industrial Supplies Catalog

Let’s Talk

Ready to get started? Or have questions about any of our products or services? Fill out the form and a representative will contact you promptly.

About AK Material Handling Systems

We deliver value to our customers by providing the absolute best combination of quality products, helpful customer service and competitive pricing. We specialize in warehouse layout & design, pallet rack systems, engineered sales, mezzanines, modular offices and completed turn-key warehouse systems. For more information email us or call (800) 722-5908